Technical parameters
- Catchment area: 14.660 km2
- Reservoir capacity: 348.5 million m3
- Reservoir surface area at full supply level: 13.13 km2
- Full supply level: 160 m
- Minimum operating level: 150 m
- Flood control storage: 150 million m3
- Regular flood control storage: 112 million m3
- Installed capacity: 260 MW
- Mean annual electricity: 1,018.61 million kWh
- Dam crest length: 513 m, dam crest width: 8 m
- Dam height: 84.5 m (from lowest bedrock)
- The elevation of the dam: 162.8m (from the sea level)
- A power plant containing four 65 MW Francis turbines (total installed capacity of 260 MW), is designed for a maximum water head of 72.02 m
- A 220kV transmission line of 65 km long connecting to Vietnam national grid
Project schedule
Key milestones of the project
- Commencement of main civil works: November 2012
- River diversion: December, 2013
- Impoundment: December, 2016
- Power Generation by unit No. 1: February 15th, 2017
- Power Generation by unit No. 4: June 20th, 2017