On February 8, 2017, at the office of Trung Son Hydropower Project Management Board, the 2016 Summary and 2017 Planning Conference was held by Trung Son Hydropower Company Limited…
General Director of Power Generation Corporation 2 checked the progress of Trung Son Hydropower Project
On February 4, 2017 the mission of Power Generation Corporation 2 (EVNGENCO2) led by Mr. Ngo Viet Hai – General Director had worked and checked the progress of the…
On February 4, 2017 the mission of Power Generation Corporation 2 (EVNGENCO2) led by Mr. Ngo Viet Hai – General Director had worked and checked the progress of the…
Trung Son Hydropower Reservoir to Impound Water
Trung Son Hydropower project schedules to close the diversion culvert for reservoir filling at the end of December 2017. Hydropower reservoir filling is to use a dam to impound…
Trung Son Hydropower project schedules to close the diversion culvert for reservoir filling at the end of December 2017. Hydropower reservoir filling is to use a dam to impound…
Energization of 220kV Switchyard of Trung Son Hydropower Plant
220kV Switchyard of Trung Son Hydropower Project was formally energized at 2:52 AM on December 17, 2016. The working teams of Trung Son 220kVSwitchyard, Nho Quan 500kV Switchyard and…
220kV Switchyard of Trung Son Hydropower Project was formally energized at 2:52 AM on December 17, 2016. The working teams of Trung Son 220kVSwitchyard, Nho Quan 500kV Switchyard and…
Unit 2 Rotor of Trung Son Hydropower Plant Successfully Assembled
The rotor of Unit 2 of Trung Son Hydropower Project was successfully assembled on December 20, 2016. The rotor of Unit 2 is 250 tons heavy with a diameter…