On February 16, 2017, a mission from Vietnam Electricity (EVN) led by Mr. Nguyen Cuong Lam- Deputy General Director as the team leader, visited and checked the implementation progress of Trung Son Hydropower Project following Unit 1 power generation and connection to the National Electricity Grid. The mission also included Department of Construction Management and Department of Investment and Construction Management of GENCO2.
Receiving and working with the mission, from the side of Trung Son Hydropower Company Limited (TSHPCo), were Mr. Vu Huu Phuc- Company Chairman cum Director, the Board of Directors, Project Management Board; Specialist Departments of the Company, Representatives of Design Consultant, Supervision Consultant and Construction Contractors.
Having checked the implementation progress at site and listened to representatives of the Employer, Contractors, Consultants reporting on implementation progress of Trung Son Hydropower Project, Mr. Nguyen Cuong Lam, on behalf of EVN leaders, commended the Employer, Contractors and Consultants for their efforts in constructing Trung Son Hydropower Project, especially for connecting Unit 1 to the National Electricity Grid on February 15, 2017. Besides, EVN Deputy General Director also requested the Employer, Contractors and Consultants to collaborate to solve problems for power generation by remaining Units and completion of the project according to the assigned schedule.
On behalf of the Employer, Contractors, Supervision Consultant, Design Consultant, Mr. Vu Huu Phuc- Company Chairman cum Director received directive comments of EVN leader, and expressed determination to direct, coordinate with concerned parties to finish work items of the project as per assigned schedule.
Some pictures of EVN Deputy Director at progress checking visit at Trung Son Hydropower Project
Mr. Nguyen Cuong Lam- EVN Deputy General Director (the 5th to the left) checking the construction progress of spillway- Trung Son Hydropower Project
EVN Deputy General Director checking the system at central control room- Trung Son Hydropower Project
Checking construction of powerhouse tailrace – Trung Son Hydropower Project