The rotor of Unit 2 of Trung Son Hydropower Project was successfully assembled on December 20, 2016.
The rotor of Unit 2 is 250 tons heavy with a diameter of 7.5m. Before installing the rotor, the Contractors had completed the installation of the turbine, stator, crane, lifting system and insulation testing.
Rotor of Unit 2 at Trung Son Hydropower Plant had been successfully assembled at 8:00 AM of December 20, 2016
This is great efforts of Trung Son PMB and the Contractors and is an important prerequisite for the generation of the Unit 1 and Unit 2 in the first Quarter 2017.
Right after assembling the rotor of Unit 2, under the request of Trung Son PMB, the Contractor actively complete auxiliary work items preparing for generation of unit 1 & 2 and equipment erection for assembling of Units 3&4’s rotor .